Ask Microeconomics Expert

Assignment

In this exercise, you play the role of Shawna, a project manager for ZAP Pharmaceutical Company. Currently, you are managing a large IT project in the healthcare industry for ZAP. Your project is to refurbish an existing office building, install the IT infrastructure, and outfit the area for use as a new telephone answering hub for your company. You took over this project a week ago from John, the previous project manager. John had overseen the project since its inception.

This project is in the execution phase, with the refurbishing and installation of the infrastructure currently being done in concert with each other. All of the new office equipment is on order and is scheduled for delivery on the day after the refurbishment and infrastructure work are scheduled for completion. The overall work progress is about three quarters finished. Senior management is pleased with the progress of the project so far.

There are four vendors working with you on the project. Bear's Construction Company is handling all the refurbishment. This work includes all structural work, drywall, and electrical work in the building. Anne's Interior Design is doing the carpeting, painting, and cubicle work. Roxy's IT Services is installing all IT components, including servers, IT cabling, and a wireless network. Sheba's Office Equipment is providing all desks, computers, and phones. All contracts associated with this project are fixed price contracts.

Since taking over for John, you have had a number of contractual issues arise associated with this project. You have delayed making any decisions about these issues, hoping they would work themselves out. Today, a third contractual issue was brought to your attention.

Realizing you can no longer postpone action on these issues, you call a meeting of your project team. You project team is made up of three individuals. Iris is the future manager of the telephone hub. Tony is the IT lead on the project. Phil is the facility specialist assigned to your team.

You describe each of the three issues to the team and ask for input.

Bear's Construction Company is making a claim that it is not responsible for inspections required by the local township. Bear has produced a memo signed by John during negotiations that states that ZAP is responsible for all permits and inspections. However, a quick review of the contract shows that Bear is responsible for all inspections. Failure to resolve this issue will likely delay the project at least 1 week, because Bear is making no effort toward arranging for the required inspections.

Anne's Interior Design has brought to you another issue. In the contract, under the section labeled Special Conditions, it states that carpeting must meet a specific wear rating. In the same contract, in the General Conditions section, the contract prohibits the use of any nongeneric materials within the work of the contract. This would include carpets with special wear rating, because these would be nongeneric materials. Anne has already purchased and begun the installation of the generic carpet that does not meet the wear rating.

Sheba's Office Equipment has informed you of a minor typographic error in the contract with you to provide office equipment for this project. In the contract, it states Sheba shall be paid as follows.

$350,000 (Three hundred and fifty thousand dollars)

Sheba apologizes for any inconvenience this may have caused and is awaiting the payment of $350,000. The company further states $350,000 would have not likely even begun to cover the shipping costs. Sheba informs you that it will ship the office equipment when the remainder of its fee is received. After receiving this information from Sheba, you priced out the cost of the office equipment from other vendors and the average price was $40,000.

Your Role

As the project manager, the project team is looking to you for direction on each of these issues. Review the comments of the key players, consult the grading rubric below and then answer the following questions.

Is Bear or is ZAP responsible for the inspections? What is a reasonable course of action given that the project may have to be delayed a week or more?

What carpet should be installed? Should work be stopped to evaluate this issue? What do you do to resolve this?

How much is owed to Sheba? What actions would you take as the project manager?

Deliverable: Turn in a three- to five-page paper outlining your complete responses to the above questions.

Microeconomics, Economics

  • Category:- Microeconomics
  • Reference No.:- M91942325
  • Price:- $35

Priced at Now at $35, Verified Solution

Have any Question?


Related Questions in Microeconomics

Question show the market for cigarettes in equilibrium

Question: Show the market for cigarettes in equilibrium, assuming that there are no laws banning smoking in public. Label the equilibrium private market price and quantity as Pm and Qm. Add whatever is needed to the mode ...

Question recycling is a relatively inexpensive solution to

Question: Recycling is a relatively inexpensive solution to much of the environmental contamination from plastics, glass, and other waste materials. Is it a sound policy to make it mandatory for everybody to recycle? The ...

Question consider two ways of protecting elephants from

Question: Consider two ways of protecting elephants from poachers in African countries. In one approach, the government sets up enormous national parks that have sufficient habitat for elephants to thrive and forbids all ...

Question suppose you want to put a dollar value on the

Question: Suppose you want to put a dollar value on the external costs of carbon emissions from a power plant. What information or data would you obtain to measure the external [not social] cost? The response must be typ ...

Question in the tradeoff between economic output and

Question: In the tradeoff between economic output and environmental protection, what do the combinations on the protection possibility curve represent? The response must be typed, single spaced, must be in times new roma ...

Question consider the case of global environmental problems

Question: Consider the case of global environmental problems that spill across international borders as a prisoner's dilemma of the sort studied in Monopolistic Competition and Oligopoly. Say that there are two countries ...

Question consider two approaches to reducing emissions of

Question: Consider two approaches to reducing emissions of CO2 into the environment from manufacturing industries in the United States. In the first approach, the U.S. government makes it a policy to use only predetermin ...

Question the state of colorado requires oil and gas

Question: The state of Colorado requires oil and gas companies who use fracking techniques to return the land to its original condition after the oil and gas extractions. Table 12.9 shows the total cost and total benefit ...

Question suppose a city releases 16 million gallons of raw

Question: Suppose a city releases 16 million gallons of raw sewage into a nearby lake. Table shows the total costs of cleaning up the sewage to different levels, together with the total benefits of doing so. (Benefits in ...

Question four firms called elm maple oak and cherry produce

Question: Four firms called Elm, Maple, Oak, and Cherry, produce wooden chairs. However, they also produce a great deal of garbage (a mixture of glue, varnish, sandpaper, and wood scraps). The first row of Table 12.6 sho ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As