Three estimators at Tech Engineering have come up with the estimates of cash flows as shown in the table below for a project with a life of 10 years. Compute the expected NPW at 20%.
Data Estimator I Estimator II Estimator III
First Cost,$ 5000 8750 7500
Benefits / Year, $3750 40003000
Salvage Value 1750 1000 5000
A. $14,033 B.$8356.92 C. $15,830 D. $15,391