the construction time for a bridge depends on the weather. the project is expected to take 250days if the weather is dry and hot. if the wather is damp and cool it will take 350days. otherwise, it is expected to take 300 days. historical data suggest that the probability of cool, damp weather is 30% and that of dry, hot weather is 20%. find the projects probability distribution. compute the Expected completion time.