1) Provide and show all answers and step by step work to obtain the answer, not skipping any steps. Show all equations, acronyms (ie ETC, ACWP, etc), and if applicable, a description of how you came to the answer.
Problem:
Bob establishes X/Y 50/50 EV technique for a work package valued at 80 hours. At the end of the 1st month, he has not spent 30 hours against this WP, but he has not completed the work. Current BCWP hours for the WP are?