The board of directors of Ogle Construction Company is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Ogle's controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information:
1. Ogle commenced doing business on January 1, 2013.
2. Construction activities for the year ended December 31, 2013, were as follows:

Total Contract Billings Through Cash Collections
Project Price 12/31/13 Through 12/31/11
A $ 510,000 $ 340,000 $ 310,000
B 700,000 210,000 210,000
C 475,000 475,000 390,000
D 200,000 100,000 65,000
E 460,000 400,000 400,000
$2,345,000 $1,525,000 $1,375,000

Contract Costs Estimated
Incurred Through Additional Costs to
Project 12/31/13 Complete Contracts
A $ 424,000 $101,000
B 195,000 455,000
C 350,000 -0-
D 123,000 97,000
E 320,000 80,000
$1,412,000 $733,000

3. Each contract is with a different customer.
4. Any work remaining to be done on the contracts is expected to be completed in 2014.

Instructions
(a) Prepare a schedule by project, computing the amount of income (or loss) before selling, general, and administrative expenses for the year ended December 31, 2013, which would be reported under:
(1) The completed-contract method.
(2) The percentage-of-completion method (based on estimated costs).
(b) Prepare the general journal entry(ies) to record revenue and gross profit on project B (second project) for 2013, assuming that the percentage-of-completion method is used.
(c) Indicate the balances that would appear in the balance sheet at December 31, 2013 for the following accounts for Project D (fourth project), assuming that the percentage-of-completion method is used.
Accounts Receivable
Billings on Construction in Process
Construction in Process
(d) How would the balances in the accounts discussed in part (c) change (if at all) for Project D (fourth project), if the completed-contract method is used?

Accounting Basics, Accounting

  • Category:- Accounting Basics
  • Reference No.:- M9903852
  • Price:- $45

Guranteed 36 Hours Delivery, In Price:- $45

Have any Question?


Related Questions in Accounting Basics

Question - nancy gives her grandson sean 20 acres of land

Question - Nancy gives her grandson, Sean, 20 acres of land. Her tax basis in the land is $25,000. Nancy's marginal tax rate for the current year is 45%; her grandson's is 25%. Its fair market value was $575,000 at the d ...

Question - for the next six months rushford designs

Question - For the next six months, Rushford Designs projects the following information (in units).   July Aug. Sept. Oct. Nov. Dec. Retail demand 300 300 450 600 600 600 Dealer demand 600 750 1,050 1,200 1,200 1,350 Sho ...

Question what discoveries have you made in your research

Question: What discoveries have you made in your research and how does this information inform your ability to evaluate effective coaching and its impact on organizations? Consider these guiding questions: 1. What core c ...

Question - lionel is an unmarried law student at state

Question - Lionel is an unmarried law student at State University Law School, a qualified educational institution. This year Lionel borrowed $24,000 from County Bank and paid interest of $1,440. Lionel used the loan proc ...

Question - use the following information for transactions

Question - Use the following information for transactions 18 and 19. You are the SELLER. You sell merchandise on account for $12,000. The merchandise cost you $7,200. The terms are FOB shipping, 2/10, n/30. You receive a ...

Question - oakbrook company is subject to a 30 income tax

Question - Oakbrook Company is subject to a 30% income tax rate. The following data pertain to the period just ended when the company produced and sold 45,000 units: Sales revenue - $1,350,000 Variable costs - 810,000 Fi ...

Question - blacken company manufactures motorcycles the

Question - Blacken Company manufactures motorcycles. The company's management accountant wants to calculate the fixed and variable costs associated with utility cost incurred by the factory. Data for the past five months ...

Question - doug is considering investing in one of two

Question - Doug is considering investing in one of two partnerships that will build, own, and operate a hotel. One is located in Canada and one is located in Arizona. Assuming both investments will generate the same befo ...

Question - gemmex inc is a consulting company that

Question - Gemmex Inc. is a consulting company that specializes in systems design and implementation. The following transactions are recorded by Gemmex during July, its first month of operations. July 1: Issued common sh ...

Question -describe the basic characteristics of the cash

Question - Describe the basic characteristics of the cash basis and the accrual basis of accounting. Identify the reasons why adjusting entries must be made. Explain the purpose of deferral adjustments and accrual adjust ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As