Ask Question, Ask an Expert

+61-413 786 465

info@mywordsolution.com

Ask Auditing Expert

In planning the audit work of the Ministry, the audit staff member collected these details relating to the construction of an office complex.

1. In September 1994, the Ministry requested the assistance of the Ministry of Works, for the preparation of plans and preliminary drawings to ‘set up a building to accommodate its departments' of approximately 6000m2 at an estimated budgeted cost of Rs 50 million.

2. In September 1995, an architectural competition was launched with a view to have the best design and the winner was to be engaged as the Consulting Architect subsequently. The design was prepared on a project area of approximately 12,827m2, with costs estimated at Rs 127 million. In August 1997, the winner of the design competition was appointed the Consulting Architect and he was to charge a fee of 6 per cent of the construction cost.

3. The Consulting Architect discussed major requirements directly with the client ministry and brought major modifications to the design without informing the Ministry of Public Infrastructure.

4. In September 1997, the client ministry requested changes to be made to the proposed building to accommodate parking for 100 cars and making provision for three additional floors for future expansion.

5. In February 1999, confirmed that funds of Rs 285 million were available for the construction of the building that would comprise of three levels of approx. 13,460 m2 and provision of three additional floors.

6. In June 1999, the client proposed further modifications, semi-basement to be full basement and finished to be upgraded. The costs were estimated at Rs 326 million.

7. In September 1999, the client requested for the project cost to be curtailed to Rs 175 million. After The Central Tender Board had given its approval, the consultants brought modifications to the design and plan of the buildings and prepared the tender documents.

8. In April 2002, the contract was awarded to XYZ Builders Ltd at a contract price of Rs 161,310,621 and contract had to be completed on 17 January 2004. Soon after, i.e in August 2002, the client ministry again requested major modifications to accommodate two other units on both the first and second floors in place of the administrative block. Further modifications were made to the revised plan in July 2003 and March 2004 to consider the urgent needs of the client.

9. The project was completed and Consulting Architect issued the Practical Completion Certificate in October 2005. All works were completed on 21 August 2006.

10. In the Cost Report dated August 2005, the Quantity Surveyor mentioned the following extra costs related to the project:

a. Loss & expense claim from the contractor of Rs 44 million;
b. Claim of Rs 25 million for running the site beyond practical completion date;
c. Claim of Rs 6 million representing increases in costs of materials and labour;
d. Loss and expense claim from the subcontractor for electrical works of Rs 15 million.
11. On September 2007, the Central Tender these additional payments were approved
a. Consulting Architects - Rs 3,857,230 (inclusive of VAT)
b. Project Manager - Rs 1,739,130 (inclusive of VAT)
c. M&E Consultant - Rs 915,478 (inclusive of VAT)
d. Structural Consultant - Rs 87,000
e. Quantity Surveyor Consultant - Rs 561,000
12. The final cost of the project was much higher than the contractual price of Rs 161,310,621.

Required

(i) List down the audit work you would perform in respect of the above capital project.

(ii) List down 10 (ten) shortcomings that you could bring to the attention of the Accounting Officer of the ministry following the examination of any capital project. You may use the above- mentioned case as a reference.

Auditing, Accounting

  • Category:- Auditing
  • Reference No.:- M9588150

Have any Question?


Related Questions in Auditing

Group assignment themedeveloping an audit program for a

Group Assignment Theme: "Developing an Audit Program for a selected ASX listed Company" The objective of this group assignment is to provide you with an opportunity to design a "risk-based" audit program for a real world ...

Assignment -background you are an intermediate member of

Assignment - Background: You are an intermediate member of your firm's audit team and the audit partner has asked you to assist with the planning stage of the audit for a small client. You have access to the preliminary ...

Audit assurance and compliance assignment -topic how is

Audit, Assurance and Compliance Assignment - Topic: How is Enhanced Auditor Reporting being embraced in Australia? Background and Context: Since 2016, there has been a strong push to improve the quality of audit reportin ...

Assignment overviewassignment descriptionchoose a publicly

Assignment Overview Assignment Description Choose a publicly traded company, and research its annual report. (If you cannot find it online, you can go to the U.S. securities and Exchange Commission Web site and locate a ...

Questionit has been recommended that lsquoaudit working

Question It has been recommended that ‘Audit working papers should always be sufficiently complete and detailed to enable an experienced auditor with no previous connection with the audit subsequently to ascertain from t ...

Audit assurance and compliance assignment -topic how is

Audit, Assurance and Compliance Assignment - Topic: How is Enhanced Auditor Reporting being embraced in Australia? Research Assessment: Download an annual report of an ASX listed company that is in the S&P/ASX 300 list. ...

Rofessional auditing assignmentyou are required toa draft

ROFESSIONAL AUDITING ASSIGNMENT You are required to: a) Draft an audit planning memorandum highlighting: i) the legal and other considerations that need to be considered by your firm as the new auditor of SBL; ii) the ma ...

Question - research paper on the knowledge of auditing

Question - Research Paper on the knowledge of Auditing Concepts, you can choose any one of the following two titles: Title: AUDITING ENVIRONMENT Identify the risk and liability factors in financial statement audits. Rela ...

Topic how is enhanced auditor reporting being embraced in

Topic: How is Enhanced Auditor Reporting being embraced in Australia? Background and Context: Since 2016, there has been a strong push to improve the quality of audit reporting. Listed entities now have to report on "key ...

Assignment total quality management -question 1 -a a

Assignment total quality management - QUESTION 1 - A. A defense contractor, manufacturers rifles for the military. The military has exerting quality standards that the contractor must meet. The military is very much plea ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As