At an activity level of 8500 machine hrs. a month. Doe corp's total variable production engineering cost is $700,000 and its total fixed production engineering cost is $150,000. What would be the total production engineering cost per unit, both fixed and variable, at an activity level of 8700 machine hours in a month? assume this level of activity is within the relevant range.(do not round intermediate calculations).