How should earned but unbilled revenues at the balance sheet date on a long-term construction contract be disclosed if the percentage-of-completion (POC) method of revenue recognition is used?
Provide the required journal entries for this project.
Example
POC Revenue 1,5 Mio
Project costs 1,0 Mio
Billings 1,8 Mio
Unearned 0,3 Mio