Given:
Period Project cash flows
(n) A B C D
0 $(5,000.00) $(2,000.00) $4,500.00 $(3,500.00)
1 $5,800.00 $(4,400.00) $(6,000.00) $1,000.00
2 $12,400.00 $7,000.00 $2,000.00 $5,000.00
3 $8,200.00 $3,000.00 $4,000.00 $6,000.00
Compute the net future worth of each project at i=13%