For Savage Inc. variable manufacturing overhead costs are expected to be $20,000 in the first quarter of 2005 with $2,000 increments in each of the remaining three quarters. Fixed overhead costs are estimated to be $35,000 in each quarter. Prepare the manufacturing overhead budget by quarters and in total for the year.