Examine the following EVM data for the Acme project, a hypothetical construction project, to view information on the past and future performance:

*Cumulative planned value (PV) = 550

*Cumulative earned value (EV) = 475

*Cumulative actual cost (AC) = 525

*Budget at completion (BAC) = 1000

After evaluating the Acme project, do the following:

1. Calculate the cost variance (CV), schedule variance (SV), cost performance index (CPI), and schedule performance index (SPI). Using these four metrics, briefly explain whether the project is ahead or behind for cost and schedule performance.

2. Using the results from the first question, calculate the Estimate at Completion (EAC) and Variance at Completion (VAC). Analyze the results and explain whether the project is likely to overrun or under run the baseline plan and by how much.

 

*Make sure that you include formulas in the spreadsheet so that calculations can be checked!

Business Economics, Economics

  • Category:- Business Economics
  • Reference No.:- M91521012

Have any Question?


Related Questions in Business Economics

Match the definitionconsumer surplusproducer surplusthe

Match the Definition Consumer Surplus Producer Surplus The difference between the amount that buyers would be willing and able to pay for a good and the actual amount the buyer pays The difference between the minimum amo ...

We went over this problem in class but i dont understand

We went over this problem in class but I don't understand what exactly the professor did, so could someone explain step by step how to approach a problem like this? I have a homework assignment with problems similar to t ...

Demand qd900-2p3pa04m15asupply qs45500-05pqd quantity

Demand: Qd=900-2P+3Pa+0.4M+1.5A Supply: Qs=45500-0.5P Qd = Quantity demanded P = Price of Myvi car (in RM) Pa = Price of Produa Asia (in RM) M = Average consumer income (in RM) A = Promotional expenses Qs= Quantity deman ...

Suppose the production function for a firm is given

Suppose the production function for a firm is given by:  q=4L 0.5 K 0.25 . In the short run, the firm has  16 units of capital.  Find the Marginal Product of Labor (MP L ). Fill in the appropriate numbers in the function ...

Suppose a bond with no expiration date has a face value of

Suppose a bond with no expiration date has a face value of $10,000 and annually pays a fixed amount of interest of $900. a. In the table provided below, calculate and enter either the interest rate that the bond would yi ...

Determine the sample size needed to construct a 90

Determine the sample size needed to construct a 90?% confidence interval to estimate the average GPA for the student population at a college with a margin of error equal to 0.5. Assume the standard deviation of the GPA f ...

Currently fringe benefits make up about 30 of us workers

Currently, fringe benefits make up about 30% of U.S. workers' total compensation. Suppose the U.S. government decides to tax fringe benefits as ordinary income. How might this affect the level of fringe benefits as a sha ...

What are some challenges in delivering health services in

What are some challenges in delivering health services in the peripheral areas?

Magenta corporation wants to raise 508 million in a

Magenta corporation wants to raise 50.8 million in a seasoned equity offering, net of all fees. Magenta stock currently sells for $14 per share. The underwriters will require a spread of $.50 per share, and indicate that ...

In what kind of economy is a central planning board or

In what kind of economy is a central planning board or commission typically used to answer the basic economic questions?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As