Elroy had been with Barnes Machine Company a year since finishing a BS in industrial engineering (IE). Barnes had been in business for over 50 years, but the company had only recently moved from Detroit to Gainesville, Georgia. The public reason for the move was the economics of the old facility. Privately, based on comments he had heard, Elroy believed a shift to nonunion labor was a larger motive. Elroy’s boss is the production supervisor, Mr. Hill. Because the plant and the workforce are new, Elroy has been conducting time-and-motion studies to establish new production standards. While these were clearly needed, Elroy was impatient to apply other IE tools he had studied.

One Friday, Mr. Hill asked Elroy to attend a 10 a.m. meeting on Monday. Monday morning, Elroy was surprised to join not only Mr. Hill and John Blackburn, the head of manufacturing engineering, but also Mr. Simkins, the head of marketing and several others from sales and marketing. Most surprising was the attendance of the company’s CEO, Mr. Barnes, Jr. The meeting’s purpose was to consider a request for proposal (RFP). As Mr. Simkins quickly pointed out, the request came from one of Barnes’s most significant customers. The problem, and the reason for the special meeting, was that a successful bid would exceed current production capabilities. Mr. Simkins, in summarizing, said, “Fortunately Mr. Barnes was farsighted enough to have our new facility built with room for expansion.” Mr. Hill agreed: “I see no reason why we should not bid on this proposal. Of course, as John pointed out, we will need new production capability. While this RFP calls for a five-year delivery plan, the total number of parts has not been specified. Since Simkins believes the data will be available before the final proposal deadline, I suggest that we examine the economics of the various different manufacturing alternatives. To that end, I intend to have Elroy here start that study immediately.” Mr. Barnes ended the meeting with, “I’m sure that not bidding won’t hurt our other business with them, but they have been a steady customer since my father started the company and I really would like to help them. Besides, whenever we have added new manufacturing capacity, Simkins has managed to sell it to someone. So whatever you do, Hill, don’t let Elroy be too pessimistic. Let’s get on with it. I expect a preliminary evaluation in two weeks. By the way, John, don’t forget about all that extra equipment we have stored from the old plant. You may find something there that will help keep the cost down.”

During the next several days, Elroy met several times with Mr. Hill and John Blackburn. John, who had joined the company after it moved, drove to a warehouse in Atlanta to inspect the stored equipment. In a meeting Wednesday, John said that only a new engine lathe would be required. Hill said, “If that’s all we need to bid this job, Mr. Barnes will be very pleased. After all, what will it cost, 15 or 20 thousand?” “We can probably find one in that price range, Mr. Hill,” John said, “but if we are going to consider this as a long-term investment that Mr. Simkins will market for us, I think we should seriously consider one of the automated systems that have become available in the past few years. Remember, this type of equipment usually lasts a long time. I am sure that it will still be serviceable long after we complete this contract.” “OK, John, your point is well made,” Mr. Hill replied. “Elroy see what you can find that will do the job. Check with John on the specs, but take a close look at the economics for us.” During the next few days, Elroy found that there were basically four different possible machine types that would do the job ranging from the traditional manual engine lathe to a computer-controlled lathe with robotic load/unload and tolerance checks. From the manufacturers, he obtained the information contained in Table 10-1.

Table 10-1 Cost Data

Machine Type                         Purchase Cost             Annual Maintenance Cost

A. Manual                               $18,000                       $1,350

B. Semiautomatic                    27,000                         2,430

C. Automatic                          64,000                         4,250

D. Automatic with                  120,000                       14,400

robotic load/unload

Machines A and B would each require a full-time operator. A single operator could service two of Machine type C, and Machine type D would require no operator at all. After consulting with John about the skill level required, Elroy checked with accounting and found that an operator would be paid at $14.29 an hour. A 25% incentive is added to base pay for employees on the second or third shifts. In addition, fringe benefits would run 63% of base pay, and manufacturing overhead would be assigned at a rate of 47% of the operator’s direct pay. Accounting had indicated that they would try to classify the equipment in the 5-year life category for tax depreciation purposes. Mr. Hill, John, and Elroy decided that the analysis should be based on production runs of 1000 pieces due to uncertain availability of storage space. Elroy noted that each of the machines has a different production rate and setup procedure. Each manufacturer claims an expected life of about one million pieces. John pointed out that the machines all use the same cutting technique, which implies that the tool and material costs should be about the same. Elroy summarized this in Table 10-2.

Table 10-2 Production Data

Machine                      Setup Cost      Production Rate          (Material +Tool Cost)/piece

                                                            (Pieces/Hour)            

A                                 $750                6 pieces                       $0.50

B                                 1000                12 pieces                     0.50

C                                 3000                30 pieces                     0.50

D                                 6000                30 pieces                     0.50

John pointed out that there is a part currently purchased from an outside vendor that could be produced on this equipment. He estimates the setup cost to be about the same and the production rates to be approximately twice as many pieces per hour for Machine A, about 50% greater for Machine B, and remaining about the same for Machines C and D. Machine tool and material cost would run about $0.70 a unit. When Elroy checks with accounting, he finds that they purchased about 7,000 of the parts last year. Marketing expects that to increase to 8,000 parts this year and remain steady for a while. Accounting tells him that the average cost per purchased part is $4.26. In previous economic studies of capital purchases, Elroy has been told to use an interest rate of 15%. He believes that he should do the same here. Friday afternoon Elroy sits down to begin his analysis. He knows that everyone at the meeting next Monday will expect him to have an answer and that it is very likely that his report will determine whether or not Barnes responds to the RFP.

Discussion Questions:

1. What financial parameters/criteria would you consider in analyzing this problem?

 

2. Which machine should be chosen and why?

Financial Accounting, Accounting

  • Category:- Financial Accounting
  • Reference No.:- M92039693

Have any Question?


Related Questions in Financial Accounting

Case study - the athletes storerequiredonce you have read

Case Study - The Athletes Store Required: Once you have read through the assignment complete the following tasks in order and produce the following reports Part 1 i. Enter the business information including name, address ...

Scenario assume that a manufacturing company usually pays a

Scenario: Assume that a manufacturing company usually pays a waste company (by the pound to haul away manufacturing waste. Recently, a landfill gas company offered to buy a small portion of the waste for cash, saving the ...

Lease classification considering firm guidance issues

Lease Classification, Considering Firm Guidance (Issues Memo) Facts: Tech Startup Inc. ("Lessee") is entering into a contract with Developer Inc. ("Landlord") to rent Landlord's newly constructed office building located ...

A review of the ledger of oriole company at december 31

A review of the ledger of Oriole Company at December 31, 2017, produces these data pertaining to the preparation of annual adjusting entries. 1. Prepaid Insurance $19,404. The company has separate insurance policies on i ...

Chelsea is expected to pay an annual dividend of 126 a

Chelsea is expected to pay an annual dividend of $1.26 a share next year. The market price of the stock is $24.09 and the growth 2.6 percent. What is the cost of equity?

Sweet treats common stock is currently priced at 3672 a

Sweet treats common stock is currently priced at $36.72 a share. The company just paid $2.18 per share as its annual dividend. The dividends have been increasing by 2,2 percent annually and are expected to continue doing ...

Highway express has paid annual dividends of 132 133 138

Highway Express has paid annual dividends of $1.32, $1.33, $1.38, $1.40, and $1.42 over the past five years, respectively. What is the average divided growth rate?

An investment offers 6800 per year with the first payment

An investment offers $6,800 per year, with the first payment occurring one year from now. The required return is 7 percent. a. What would the value be today if the payments occurred for 20 years?  b. What would the value ...

Oil services corp reports the following eps data in its

Oil Services Corp. reports the following EPS data in its 2017 annual report (in million except per share data). Net income $1,827 Earnings per share: Basic $1.56 Diluted $1.54 Weighted average shares outstanding: Basic 1 ...

At the start of 2013 shasta corporation has 15000

At the start of 2013, Shasta Corporation has 15,000 outstanding shares of preferred stock, each with a $60 par value and a cumulative 7% annual dividend. The company also has 28,000 shares of common stock outstanding wit ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As