Earned Value, PPBE & Budget EXTRA CREDIT Exam

1) Which one of the following best describes the conditions under which a P-40a budget exhibit is required to be submitted?
When the line item is part of budget activities 4, 5, or 7
When the line item covers advance procurement funds for a weapon system
When the line item is an aggregation of different end items requiring funding of less than $5 million apiece
When the line item funding is $5 million or more in the budget year

2) Which one of the following contracts most likely would NOT require contract performance reporting by a Contract Performance Report (CPR)?
18-month Fixed-Price Incentive Fee Procurement contract valued at $165 million (then year dollars)
36-month Cost Plus Award Fee RDT&E contract valued at $54 million (then year dollars)
24-month Cost Plus Fixed Fee RDT&E contract valued at $3.8 million (then year dollars)

3) All of the following are characteristics of an effective reclama, EXCEPT:
Is concise
Provides specific, believable impacts on the program
Uses technical jargon and acronyms
Specifically addresses reasoning for proposed funding cut

4) Which one of the following statements is FALSE concerning the P-3a budget exhibit?
It includes a schedule for installation of modification kits
It may display RDT&E funding information as well as procurement funding information
It provides a listing of all items that will be purchased with advance procurement funds
It specifies the quantity of items funded each year, when applicable

5 Which of the following is NOT a primary input to the Programming Phase of the PPBE process ?
Fiscal Guidance (FG)
Combatant Commander's Integrated Priority Lists (IPLs)
National Military Strategy (NMS)

6) The budget exhibit that provides a schematic display of major program milestones for a project is the:
R-3
R-4
R-2
R-1

7 Place these PPBE process Budgeting Phase activities in the order in which they most commonly occur:
Reclamas to draft Resource Management Decisions (RMDs ) (budgeting phase annex) 1 2 3 4
Preparation of budget inputs by operational organizations and field activities 1 2 3 4
OSD/OMB Budget Hearings 1 2 3 4
Component preparation of the Budget Estimate Submission (BES) 1 2 3 4


8) All of the following are reasons that an acquisition program may lose funding during the PPBE process, EXCEPT:
Providing vague justification for requested funding
Failure to comply with funding policies
Clear articulation of system needs and capabilities
Funding profile absorbs excessively large share of Component's topline

9 The budget exhibit that provides detailed cost information for each project under a program element in RDT&E budget activities 4, 5, or 7 with funding of $1 million or more in any budget year is the:
R-3a
R-2
R-1
R-3

10) Which one of the following would likely trigger a question or adjustment by a budget analyst reviewing a budget request?
RDT&E program used a Procurement escalation index
Budget request is consistent with the program's current cost estimates and schedule
Program's obligations and expenditures are close to goals

11) Which one of the following is NOT a primary input to the Planning Phase of the PPBE process?
Defense Planning Guidance (DPPG)
National Military Strategy (NMS )
Chairman's Program Recommendation (CPR)
National Security Strategy (NSS)

Accounting Basics, Accounting

  • Category:- Accounting Basics
  • Reference No.:- M91026855
  • Price:- $40

Priced at Now at $40, Verified Solution

Have any Question?


Related Questions in Accounting Basics

Question what discoveries have you made in your research

Question: What discoveries have you made in your research and how does this information inform your ability to evaluate effective coaching and its impact on organizations? Consider these guiding questions: 1. What core c ...

Question requirement 1 read the article in below attachment

Question: Requirement: 1. Read the article in below attachment, and answer the questions in a paper format. Read below requirements before your writing! 2. Not to list the answers, and you should write as a paper format. ...

Question as a financial consultant you have contracted with

Question: As a financial consultant, you have contracted with Wheel Industries to evaluate their procedures involving the evaluation of long term investment opportunities. You have agreed to provide a detailed report ill ...

Question the following information is taken from the

Question: The following information is taken from the accrual accounting records of Kroger Sales Company: 1. During January, Kroger paid $9,150 for supplies to be used in sales to customers during the next 2 months (Febr ...

Assignment 1 lasa 2-capital budgeting techniquesas a

Assignment 1: LASA # 2-Capital Budgeting Techniques As a financial consultant, you have contracted with Wheel Industries to evaluate their procedures involving the evaluation of long term investment opportunities. You ha ...

Assignment 2 discussion questionthe finance department of a

Assignment 2: Discussion Question The finance department of a large corporation has evaluated a possible capital project using the NPV method, the Payback Method, and the IRR method. The analysts are puzzled, since the N ...

Question in this case you have been provided financial

Question: In this case, you have been provided financial information about the company in order to create a cash budget. Management is seeking advice or clarification on three main assumptions the company has been operat ...

Question 1what step in the accounting cycle do adjusting

Question: 1. What step in the accounting cycle do Adjusting Entries show up 2. How do these relate to the Accounting Worksheet? 3. Why are they completed at the end of each accounting period? The response must be typed, ...

Question is it important for non-accountants to understand

Question: Is it important for non-accountants to understand how to read financial statements? If you are not part of the accounting/finance function in a business what difference would it make? The response must be typed ...

Question refer to the hat rack cash flow statement 2002 in

Question: Refer to the Hat Rack Cash Flow Statement, 2002 in the text on page 17. Answer the following questions and submit to me via Canvas by the due date. 1. Cash flow from operations? 2. Cash flow from investing? 3. ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As