Auto Data manufactures custom engineering testing machine. The following 5-orders are currently in the design department:
Job Time Since Arrival Process Time Due Date
(weeks ago) (weeks) (weeks from now)
A 9 5 5
B 6 6 11
C 5 7 20
D 4 5 18
E 2 3 9
Create a schedule using the earliest due date (EDD) rule, computing the average days past due and average flow time.