Ask Question, Ask an Expert

+61-413 786 465

info@mywordsolution.com

Ask Accounting Basics Expert

Assignemnt

Problem 1

Straightforward Weighted- Average Process Costing, Step-by-Step Approach

Piscataway Plastics Company manufactures a highly specialized plastic that is used extensively in the automobile industry. The following data have been compiled for the month of June. Conversion activity occurs uniformly throughout the production process.

Work in process, June 1- 50,000 units:

Direct material: 100% complete cost of .................. $120,000

Conversion: 40% complete, cost of ............................ 34,400

Balance in work in process, June 1 ......................... $154,400

Units started during June ....................................... 200,000

Units completed during June and transferred out to finished-goods inventory ........ 190,000

Work in process, June 30:

Direct material: 100% complete

Conversion: 60% complete

Costs incurred during June:

Direct material ........................................................ $492,500

Conversion costs:

Direct labor .............................................................. $ 87,450

Applied manufacturing overhead ............................. 262,350

Total conversion costs ............................................. $349,800

Required:

Prepare schedules to accomplish each of the following process-costing steps for the month of June. Use the weighted-average method of process costing.

1.Analysis of physical flow of units.

2.Calculation of equivalent units.

3.Computation of unit costs.

4.Analysis of total costs.

Problem 2

Missing Data; Production Report; Weighted-Average

The following data pertain to the Vesuvius Tile Company for July.

Work in process, July 1 (in units) ...................................................... 20,000

Units started during July ...................................................................... ?

Total units to account for ................................................................... 65,000

Units completed and transferred out during July ................................... ?

Work in process, July 31 (in units) ................................................. 15,000

Total equivalent units: direct material ............................................. 65,000

Total equivalent units: conversion ...................................................... ?

Work in process, July 1: direct material ....................................... $164,400

Work in process, July 1: conversion .................................................... ?

Costs incurred during July: direct material .......................................... ?

Costs incurred during July: conversion ......................................... 659,400

Work in process, July 1: total cost ................................................. 244,200

Total costs incurred during July .................................................. 1,031,250

Total costs to account for ............................................................ 1,275,450

Cost per equivalent unit: direct material ........................................... 8.25

Cost per equivalent unit: conversion ................................................... ?

Total cost per equivalent unit ........................................................... 21.45

Cost of goods completed and transfered out during July .................... ?

Cost remaining in ending work-in-process inventory: direct material ...... ?

Cost remaining in ending work-in-process inventory: conversion .......... 79,200

Total cost of July 31 work in process ........................................ 202,950

Additional Information:

a.Direct material is added at the beginning of the production process, and conversion activity occurs uniformly throughout the process.

b.The company uses weighted-average process costing.

Problem 3

Straightforward Weighted- Average Process Costing, Step-by-Step Approach

2. Total equivalent units, conversion: 226,000

Problem 4

Missing Data; Production

Report; Weighted-Average

Cost remaining in ending

work-in-process inventory,

direct material: $123,750

Total cost of July 31 work in

process: $202,950

Chapter 4Process Costing and Hybrid Product-Costing Systems159

c.The July 1 work in process was 30 percent complete as to conversion.

d.The July 31 work in process was 40 percent complete as to conversion.

Required:Compute the missing amounts, and prepare the firm's July production report.

Accounting Basics, Accounting

  • Category:- Accounting Basics
  • Reference No.:- M92323099
  • Price:- $40

Priced at Now at $40, Verified Solution

Have any Question?


Related Questions in Accounting Basics

Assignment - asset misappropriation and corporate

Assignment - Asset Misappropriation and Corporate Governance For this assignment, use the Internet or Strayer databases to research and identify an organization that was a victim of asset misappropriation. Write a five t ...

Question - exter co receives terms of 210 n30 on all

Question - Exter Co. receives terms of 2/10, n/30 on all invoices from Garn Industries. On January 15, 2008, Exter purchased items from Garn for $4,200, excluding taxes and shipping costs. What amount would Exter use as ...

Question texas co established the following overhead cost

Question: Texas Co. established the following overhead cost pools and cost drivers: Budgeted Estimated Overhead Cost Pool Overhead Cost Driver Cost Driver Level Quality controls $780,000 # of inspections 26,000 inspectio ...

Question - what are the steps for finding the rate of

Question - What are the steps for finding the rate of return stock is $26.1 a share. Dividend is increased by 8 percent annually and the next dividend is expected to be $1.8.

Question evaluating the purchase of an asset with various

Question: Evaluating the Purchase of an Asset with Various Capital Budgeting Methods In this activity, you will be evaluating whether you should purchase a hybrid car or its gasoline-engine counterpart. Select two car mo ...

Question - this is an accounting problem that appears on

Question - This is an accounting problem that appears on McGraw Hill. Please help with recording the advance collection and revenue earned on the general journal. Thank you. The University of Michigan football stadium, b ...

Question - carpenter inc had a balance of 80000 in its

Question - Carpenter Inc. had a balance of $80,000 in its quality-assurance warranty liability account as of December 31, 2015. In 2016, Carpenter's warranty expenditures were $445,000. Its warranty expense is calculated ...

Question - retained earnings at 111x was 150000 and at

Question - Retained earnings at 1/1/1X was $150,000 and at 12/31/1X it was $200,000. During 2010, cash dividends of $50,000 were paid and a stock dividend of $30,000 was issued. Both dividends were properly charged to re ...

Scenario - terri has an annual contract with jackson

SCENARIO - Terri has an annual contract with Jackson Mortgage Brokers to provide property maintenance services; this includes lawn care, snow removal and parking lot maintenance. Terri spends, on average, 20 hours per we ...

Question - anwer owns a rental home and is involved in

Question - Anwer owns a rental home and is involved in maintaining it and approving renters. During the year he has a net loss of $8,000 from renting the home. His other sources of income during the year are a salary of ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As